Field guide · Compute & sovereignty

Canadian AI infrastructure tracker

Explore selected Canadian AI projects: locations, announced capacity, evidence of operation, and the next milestone to watch.

Initial selection: 5 sites across 3 provinces. Sources reviewed November 4, 2026.

Get the Tuesday briefing →

How to read this tracker: statuses reflect the dated sources below, not site inspections. An opening target is not commissioning evidence. “Operating” does not guarantee capacity available to buy.

TELUS targets over 150 MW by 2032 across its three British Columbia sites. That shared figure is not assigned to each site. Electrical MW do not directly measure computing performance.

A selective directory, not a ranking or sovereignty certification. “What to watch” questions are our analysis. Our editorial approach.

5 / 5 projects shown

Regina / Sherwood · SKAnnounced · opening unconfirmed

Bell AI Fabric — Saskatchewan

Bell

Announced capacity
300 MW base + up to 900 MW expansion planned
Source timeline
Phased development; opening unconfirmed here

The province describes a path to 1.2 GW, including power supplied by Bell for the expansion.

What to watch · Boreal analysis

Permits, power delivery and commissioning of each phase.

Rimouski · QCOperating · according to operator

TELUS Sovereign AI Factory — Rimouski

TELUS

Announced capacity
Site MW not disclosed in cited source
Source timeline
Opened September 2025, according to TELUS

TELUS reports the initial capacity sold out and says it is adding compute inventory.

What to watch · Boreal analysis

New capacity available to customers, pricing and access terms.

Kamloops · BCAnnounced · opening unconfirmed

TELUS Sovereign AI Factory — Kamloops

TELUS

Announced capacity
Site MW not disclosed in cited source
Source timeline
2026 target

Expansion of an existing data centre.

What to watch · Boreal analysis

Dated commissioning evidence and customer availability.

Vancouver · BCAnnounced · opening unconfirmed

TELUS / Westbank — M3

TELUS / Westbank

Announced capacity
Site MW not disclosed in cited source
Source timeline
Late 2026 target; scaling through 2028

Planned Mount Pleasant facility.

What to watch · Boreal analysis

Dated commissioning evidence and customer availability.

Vancouver · BCAnnounced · opening unconfirmed

TELUS / Westbank — 150 West Georgia

TELUS / Westbank

Announced capacity
Site MW not disclosed in cited source
Source timeline
2029 target

Planned downtown facility.

What to watch · Boreal analysis

Dated commissioning evidence and customer availability.